Saturday, August 25, 2007

Gas pipeline

Stages
ATI
Soil investigation for cathodic protection (CP) design stage
Stringing of pipes
Above ground production
Non destructive test (NDT) (Above ground permit 10pm-4am)
CP installation
Installation of shrink sleeves
Radio detection, trial pit, xcavation
Lowering
Tie-in
NDT
Installation of shrink sleeves
Back filling with sand
uPVC or concrete slab
Backfilling
Reinstatement
Cleaning
Testing
Final tie-in
ATO
Commissioning (Gas in)

Friday, August 24, 2007

HDD

Piloting work in progress

Jaya Glucose

Mat Piah has done installation of valve, reduce tee, and elbow using fusion technique

Pandamaran NPS16

Lowering & Tie-In in progress

MG3

Freelance work @ MG3, Petronas Penapisan Melaka, Sungai Udang

Tea everyone?

Chairman, Managing Director & Dredging International representative

JPM Office

Discussion is going very well, with Chairman Zaki Zahid.